about project

Client: Electro Sur Este
Location: Combapata, Cusco
Technology: Aclara
Date: 2015
 
We implemented the first smart metering project using PLC – TWACS technology that uses the existing electrical network and crosses the Medium and Low Voltage network, allowing the client to manage LV and MV equipment, as needed.
 
More than 5000 meters (single-phase, three-phase and reclosers) were supplied for their reading and control, destined for Distribution Electrical Substations, reclosers and Low Voltage end customers. 

Stages of the project:
 
– Basic and detail engineering
– Supply of substation communications equipment and more than 5000 smart meters
– Assembly and installation of communications equipment and smart meters in SED’s and clients in BT
– Equipment and meter configuration
– SAT tests and commissioning of the project
– Staff training
 
With this technological solution, Electro Sur Este achieves:
 
– Using technology to operate normally in the face of the global COVID-19 pandemic
– Manage the network efficiently 
– High communication reliability
– Reduce operating costs
– Generate data for better decision making
– Remote and real-time monitoring of equipment
– Improve your quality indicators (SAIDI / SAIFI)

Galería

Testimonios

Testimonios de clientes

Blog

Innovación | Noticias y Artículos

Experiencia

Otros Proyectos similares

Contact Us

We create channels to be in constant connection.

Landline: 445-7660

Atenttion: 8:30 AM – 6:30 PM

WhatssApp: (+51) 977 753 239

Atención: 24 horas

How can we help you?

We are always there for you!

Send us your inquiry and we will contact you shortly.

Are you interested in implementing the solution within a 6-month period?